The farm is air and watertight

At last, the solar panels have arrived, the last tiles have been laid around it and the last two doors installed.

The building is airtight and interior work can begin... Plasterboard, insulation and door sets are on site ready to be used tomorrow.

We are three weeks behind original schedule but we have a bit of slack in the internal works programme so with a bit of a push we should be able to catch up quickly.

 

The sample for the finishing layer of the lime render. Beautiful.