Holes

After the slow down due - mostly - to a harsh winter, the mild weather is allowing the builders to get momentum. 5 craftsmen have been working a pace finishing the doors and window openings and other bits of masonry.

Concrete being cast on top of walls to correct the slope so that it matches the original trusses. 

The two ground floor doors on the East facade have been created. They are on each side of the fire place in the kitchen. They will lead to the extension when it is build (you can see it here).

At first floor, the window sills are being cast.

The wind and rain conditions are not allowing the tiling of the roof this week.